Taweela – Fujeira Gas Pipeline

240 km Gas Pipe Line
Metal Pipes 48inch x 12m, 7.5 t
Total of 20,400 pipes

cover

PROJECT WORTH

$400 M

GAS PIPE LINE

240 KM

TOTAL PIPES

20,400

img1

Scope of Work

Phase I:

  • Custom and Port Clearance of 15000 pipe
  • Rigging + Loading + Lashing pipe
  • Transportation of the pipes from Abu Dhabi Port to Open Yard
  • Offloading
  • Stacking on Site
  • Site preparation & Management
  • HSE Management
  • Insurance

Site Preparation

  • Accommodation
  • Catering & Water Supply
  • Ridges Preparation
  • Storage Plan / Lifting Plan
  • Water Spreader
  • Waste Management
  • Security

Phase II:

Distribution of Pipes Along the Right of Way

  • Approx. 88 Km of Pipeline
  • 7350 Pipe
  • 1020 m / day

On-site Daily:

  • 25 machines
  • 40 employees
img 2